Mine Closure & Rehabilitation

  •     The conservation, protection and preservation of the natural and cultural environment are of fundamental importance
  •     The project closure plan must satisfy good international practice to ensure the health and safety of company employees and residents of the area
  •     The  main closure plan components are:
             Decommissioning and demolition of the plant and ancillary facilities
             Open pit partial backfilling, re-contouring
             Waste dump removal, drainage facility installation and area re-vegetation
             Tailings impoundment capping with appropriate material
             Saddle dams and associated drainage system maintenance
             Continuous monitoring and maintenance of the rehabilitated are
             Proposed final land uses
  •     The plan estimates an 18-month decommissioning and closure period for all mine and site infrastructure and will be updated during the project's life
  •     Overall period of five years is estimated for environmental compliance monitoring
  •     Closure and rehabilitation costs of the entire intervention area estimated to be 16 million euro
  •     Final land use for the project area will be forestry and conservation
  •     Re-vegetation will begin at the start of the project with topsoil removal and storage and the establishment of a nursery
  •     The company will guarantee the rehabilitation cost with the deposition of a letter of credit before the project's construction.
  •     Upon meeting all of the requirements of Government, the site will be released back to community for its agreed after use.
     